    CONSTRUCTION PROCESS
    Once we have used our synergy to choose the right home for you and your family, the rough draft is sent to the factory for precision engineering. Within a few days, the stamped prints are returned showing your house just how you imagined.

    When the floor plan has been signed off by you a 20% deposit is
    required to schedule the home for production.  Once built, the home is
    delivered in modules.  The modules will be set on your foundation with a crane.  When all the sections are together, your home will be about 70% complete, depending on the type, design, and options selected.

    Cherokee Homes has our own in-house construction crews that keep your home on schedule because there are no worries about sub-contractor no-shows or scheduling problems.


    BELOW IS A SAMPLE CONSTRUCTION SCHEDULE

    LAND/LOT DEVELOPMENT

    • Purchase
    • Clear Title (if not already owned)
    • Accessible to modular transporter (conduct site evaluation prior to purchase if not already owned)
    • Perk/Probe Test (or public sewer if available) conduct prior to purchase if   not already owned
    • Land Surveyed (if not already owned)


    FORMS/PROCEDURES/PERMITS

    • Select home, options ($500 non-refundable deposit is due at this time)
    • Develop and finalize prints, plans, options, finishes and specs ($300 of
        your deposit is used to draw engineered plans of your new home)
    • Contracts Signed
    • Sign-off on plans and specs
    • Secure Financing
    • Set target occupancy date
    • Establish construction activities/schedule
    • Obtain and post permits
    • Building
    • Electrical                                                       
    • Plumbing
    • Mechanical
    • Road/Culvert
    • Application for Gas/Electrical Service
    • Site Survey (stake out)


    FOUNDATION AND SITEWORK

    • Order steel beams and columns
    • Deliver dumpster and port-a-potty
    • Site preparation, remove obstacles
    • Layout and excavation
    • Form footings
    • Pour footings
    • Footing inspection
    • Install footing drains and basement stone
    • Install under slab utilities
    • Block delivery/foundation systems
    • Construct/Install foundation walls
    • Inspect foundation drains
    • Apply foundation damp-proofing and vapor barrier
    • Install anchor clips/bolts, sill plate and sealer
    • Install sump pump crock and rough plumbing
    • Install Basement windows (if ordering a basement)
    • Install Foundation drain tile and cover
    • Prep opening in floor for posts/support columns
    • Pour basement floor
    • Backfill


    SITE PREPARATION

    • Foundations and footings are completed
    • Foundation is square and level
    • Foundation and footings have passed inspection
    • Obstacles for crane and transporters have been removed
    • Access route for crane and transporters is planned
    • Crane pad is ready and firm
    • Set crew and crane schedules are confirmed
    • Bulldozer and operator scheduled and confirmed
    • Utility crews have been scheduled for turn-off/turn-on (if applicable)
    • Weather forecast for set day looks adequate
    • Payment for delivery day confirmed and available


    HOME DELIVERY AND SET

    • Modules delivered
    • Inventory and ship-loose materials checked for accuracy
    • Set Crew begins to unwrap modules, mark foundation for mating walls,
        prepare for lifting
    • Once module is set, it is checked and fastened
    • Mating Surfaces prepared
    • Wires, Pipes, Ducts and Stairs prepared
    • Posts/Support Columns Set/Installed
    • Stairs to Basement Set/Installed
    • Lift roof sections with crane
    • Lift Dormers and other roof elements
    • Make home weather-tight and secure


    EXTERIOR FINISHING

    • Siding completed
    • Masonry work completed
    • Install chimney stack (if ordered)
    • Install gutters and downspouts
    • Porches, decks and patios completed


    INTERIOR

    • Install electrical, plumbing, HVAC units
    • Inspection
    • Finish/Patch drywall
    • Finish Interior Trim and Doors/Adjust
    • Install or Seam flooring
    • Clean-Up


    EXTERIOR

    • Install exterior lights and bulbs
    • Final Grading
    • Exterior Clean-up - removal of dumpsters and Port-a-potty


    HANDING OVER THE KEYS!

        • Punch List
        • Walk through with customer
        • Final Inspection
        • Certificate of Occupancy
        • DELIVERY OF YOUR DREAMHOME KEYS!